Question
Can Columns be set on a per User basis?
Answer
Setting Column sizes, ordering, etc is set by installation, therefore one User logging into the same machine will always see the same layout they set on that particular machine. If that User uses multiple machines then they will need to configure the layout on each machine separately.
 
1.2
Reference
Work Orders
Question
Can you resize the areas of the Work Order Helpdesk Page screen?
Answer
No, but you are able to hide specific sections if desired. Click the buttons to do this.
 
1.3
Reference
Work Orders
Question
Are the Statuses of Work Orders User defined?
Answer
No, they are defined by the system.
 
 
2.     Procurement - Q & A
 
2.1
Reference
Resources/Contractors
Question
Is deactivating a Resource profile driven?
Answer
Yes, it is driven by the permissions set on the profile. If you can edit a resource then you can deactivate it.
 
2.2
Reference
Resources/Contractors
Question
How do you see deactivated resources?
Answer
Click the “Is Active?” column and select “No” to view them. Only active resources are shown by default.
 
2.3
Reference
Resources/Contractors
Question
Can you allocate Work Orders to a resource if it is PQQ unapproved?
Answer
No, a resource needs to be approved and active to receive a Work Order. You can also add the resource to the PQQ Exceptions list to enable this.
 
2.4
Reference
Resources/Contractors
Question
If a contractor (resource) type is “Is Supplier?” can it receive Reactive Work Orders?
Answer
Only contractors that have a type of “Is Contractor” can be assigned Reactive Work Orders.
 
2.5
Reference
Work Order Types/Core data
Question
Can you determine what Work Order Types are for which client when selecting Work Order Types against a resource?
Answer
No, the Procurement team should use reports to find this information out when creating and editing Resources.
 
2.6
Reference
Work Order Types
Question
Is there any harm in selecting all the Work Order Types that are associated with different clients?
Answer
Associating all Work Order Types would mean the User could then manually assign any Work Order to the Resource regardless of Work Order Type. Ideally you should assign only the relevant Work Order Types to the right Resources.
 
2.7
Reference
Resources/Contractors
Question
Is VAT entry mandatory for a resource?
Answer
Yes it is but the field accepts any alphanumeric characters, so if the VAT code is not known initially a temporary code can be entered until the information is provided.
 
2.8
Reference
Resources/Contractors
Question
Since different Currencies have been added, will the Currency field be set already for previous contractors?
Answer
Yes it will. This field is a mandatory field. For Buildings, the default currency is Great British Pounds (£).
 
2.9
Reference
Resources/Contractors/Core Data
Question
Are the Contact Types in a Contact customisable?
Answer
Yes and these can be added/edited in Core Data > Contact Types.
 
2.10
Reference
Reports
Question
Can you view when emails have failed or not been sent?
Answer
Yes, these can be viewed in the Reports module. Reports are profile specific.
 
2.11
Reference
Resources/Contractors
Question
In Rates & Availability, does the Date Range you are adding need to cover a whole year?
Answer
No, this can be set to any length you like.
 
2.12
Reference
Contracts
Question
What appears on the History tab of a contract?
Answer
Any changes that have been made to that contract where you are requested to provide a reason for the change, are recorded on the History tab.
 
2.13
Reference
Contracts
Question
Can we re-instate a cancelled PPM?
Answer
No, PPMs are handled via Contracts and as such the re-instate Agent Action will not function against PPM Work Orders.
 
2.14
Reference
Resource/Contractors
Question
Does an Internal resource have to have a PQQ?
Answer
No, only an External resource does in order to be able to raise a Work Order for them.
 
2.15
Reference
Resource/Contractors
Question
If a contractor (resource) type is “Is Supplier?” Is it available to select on an SRA?
Answer
Only contractors that have a type of “Is Contractor” can be assigned to an SRA.
 
2.16
Reference
Resource/Contractors/Asset
Question
Why is there an “Is Manufacturer” available to select if this is also available from the Asset screen?
Answer
A Resource can be multiple types. If a Manufacturer is created via the Asset screen, then it will not be possible to use this resource as a Contractor or Supplier. Should a Resource be a Contractor as well as a Manufacturer, the Resource should be created via the Resource module and not the Asset Module.
 
2.17
Reference
Resource/Contractors
Question
Is there any duplicate checking on creation of a Resource?
Answer
Yes.
 
2.18
Reference
Resource/Contractors
Question
Can’t seem to create a Branch?
Answer
This is permission based. Please see your System Administrator if you need this to be available to your profile.
 
2.19
Reference
Resource/Contractors
Question
When adding an address to a Resource is the “County” field pre-populated?
Answer
No this is a free form text field, however a number of Counties are present in the system, so the system will suggest Counties when you start to enter them.
 
2.20
Reference
SRA/Contracts
Question
“Temp Fix” on a Work Order – does this relate to “Op Fix SLR” and “Temp Fix SLR”?
Answer
No. Temp Fix on the Work Order relates to whether a temporary fix is in place at point of call logging from the Client. The SLR values relate to the time taken for the Resource to apply a Fix.
 
2.21
Reference
SRA/Contracts
Question
If you set an SRA as “PPM Only” do you get “reactive” to choose from in the Contract – “Contract Type” field?
Answer
No, this will not be an option from the drop down selection.
 
2.22
Reference
SRA/Contracts
Question
“Reactive Parts” value. Does this get calculated in invoicing?
Answer
No.  This is for information only and can be reported upon if requested. This is a ‘ceiling’ value that should be used for comparison to parts charges on Work Orders.
 
2.23
Reference
SRA/Contracts
Question
Will the “History” tab be back dated?
Answer
Yes, Contract changes are available on the “History” tab.
 
2.24
Reference
SRA/Contracts
Question
Can you change visit dates for PPM’s on a contract?
Answer
Yes, providing the PPM’s haven’t already been generated.
 
2.25
Reference
SRA/Contracts
Question
Can you change visit dates for PPM’s on a contract?
Answer
Yes, providing the PPM’s haven’t already been generated.
 
 
3.     Call Centre – Q & A
 
3.1
Reference
Filters
Question
What is the difference between “Select All” and “Select All Filter”?
Answer
“Select All” selects everything that is populated in the list whilst “Select All Filter” selects all the items that appeared after you filtered the list.
 
3.2
Reference
Work Orders
Question
Does the “Current User?” function on the Work Order Query Definition screen search for Work Orders that the current User has affected or changed?
Answer
No, it only searches for Work Orders created by the current User.
 
3.3
Reference
Work Orders
Question
Do Public Lists provide information as to what client the list contains?
Answer
No, client information should be entered into the list name or description if this is a requirement.
 
3.4
Reference
Work Orders
Question
Are the locations that appear when creating Work Orders related to Equipment Types?
Answer
Locations are only associated to Buildings, not Equipment Types.
 
3.5
Reference
Work Orders
Question
Work Order Filter – The copy to clipboard feature, does it copy everything in the filtered list or just the items highlighted?
Answer
This will copy everything that has been brought back by your query.
 
3.6
Reference
Work Orders
Question
I cannot delete a query from a Public Work Order Filter list. Why?
Answer
This is a permission based option.  Please speak to your System Administrator.
 
3.7
Reference
Work Orders
Question
Duplicate checking of a Work Order – How many days does it go back to?
Answer
15 days is the standard setting. This can be amended if necessary.
 
3.8
Reference
Work Orders
Question
Building Events – Does a message pop up as well as being visible on the Work Order?
Answer
The Building event appears on the Verification page. On attempting to save the Work Order, the User is asked to accept that the Building Events have been read. Clicking on OK to accept that the Building Events have been reviewed will then add this to the events log.
 
3.9
Reference
Work Orders
Question
Agent Actions – Is changing Caller, Reason, Assets, etc permission based?
Answer
Currently amending these is dealt with using the one permission “Can Edit Work Orders”.
 
3.10
Reference
Work Orders
Question
When re-instating a Work Order, does this then send an email out to the resource?
Answer
Not at this time. However, the User is notified on screen that the resource should be contacted to advise them of the re-instate activity.
 
3.11
Reference
Work Orders/Quotes
Question
Quotes in authorisation – Why can the authoriser see the Mark Up?
Answer
This is permission based.  Please speak to your System Administrator.
 
3.12
Reference
Work Orders/Quotes
Question
After a quote has been authorised does it then automatically assign?
Answer
No, not for quotes.
 
 
4.     Finance – Q & A
 
4.1
Reference
Invoices
Question
Are scanned invoices kept on the system?
Answer
No, only the details of the invoice are kept on the system. However, there is the ability to add a document to the invoice entry, so a scanned copy could be added if required.
 
4.2
Reference
Work Orders
Question
On the Work Order query screen, does Resource refer to contractors?
Answer
Yes, Resource refers to contractors.
 
4.3
Reference
Budgets
Question
Can Capital Budgets be imported from Excel?
Answer
Not at this time.
 
4.4
Reference
Resources/Contractors
Question
If a resource has more than one currency, do you have to make copies of that resource to apply different currencies?
Answer
Yes. You assign one Currency per Resource.
 
4.5
Reference
Work Orders
Question
Should cancelled Work Orders set the Accrual to zero?
Answer
No and for two reasons. Firstly, the Financial reports exclude cancelled Work Orders so report figures aren’t affected and secondly, the Re-instate Work Order function has been added so the accrual would also be reinstated should a cancelled Work Order be restored.
 
4.6
Reference
Invoices
Question
Does ticking the “No Further Invoice Expected?” box add a Work Order event?
Answer
No, no event is generated.
 
4.7
Reference
Invoices
Question
Is the feature of not being able to approve your own invoices (segregation of duties) hard coded or by User?
Answer
That feature is hard coded.
 
4.8
Reference
Invoices
Question
Do you have to allocate a Building when creating a new, unallocated invoice?
Answer
No you do not have to but you do have the option to select one.
 
4.9
Reference
Invoices
Question
When an invoice is submitted for payment, does the accrual value set to zero?
Answer
Yes, once all invoices on a Work Order have been set to Payment Submission (and no further invoices expected is set), the accrual sets to zero.
 
4.10
Reference
Invoices
Question
If you invalidate an invoice, does it then change the invoice to unapproved?
Answer
No, if an invoice has been invalidated then it needs to be moved to unapproved manually.
 
4.11
Reference
Invoices
Question
How does the Work Order know that no invoice is expected? (Moving to Status 5.02 Job Completed – no invoice expected)
Answer
Only Work Orders generated from a particular type of Contract would reach the status where no invoice is expected.
 
4.12
Reference
Resources/Contactors
Question
Can contractors add certificates to Work Orders?
Answer
Yes, this can be done through the system or Portal.
 
4.13
Reference
Resources/Contactors
Question
If a contractor uploads a certificate via the Portal, is an event created?
Answer
Yes and it specifically states that it was done using the Portal.
 
4.14
Reference
Resources/Contactors
Question
Do Payment Terms on a resource affect any parts of the system?
Answer
No, these are just for reference but they are User defined.
 
4.15
Reference
Resources/Contactors
Question
Can you view Work Orders by specific dates?
Answer
Yes, this is possible by using the Dates tab of the Work Order Query Definition screen.
 
 
5.     Business – Q & A
 
5.1
Reference
Core Data
Question
Does copying clients copy across all the resources associated with that client?
Answer
No, copied clients do not automatically inherit all resources.
 
5.2
Reference
Core Data
Question
Are Levels auto-associated by default?
Answer
No, the “Auto-association?” field is un-ticked by default.
 
5.3
Reference
Core Data
Question
When removing types from Core Data, such as Contact Types, does the system inform the User that an item can’t be removed if it is in use?
Answer
Yes, a warning message is displayed informing the User.
 
5.4
Reference
Core Data
Question
Can you tick or un-tick Equipment/Service types?
Answer
Yes. This is achieved in the Core Data module.
 
5.5
Reference
Core Data
Question
Are Authorisation Reasons Capital or Revenue?
Answer
Authorisation Reasons are not related to Capital or Revenue Codes. Assuming the permissions are set, they appear when Approving or Rejecting Work Orders.
 
5.6
Reference
Core Data
Question
Are Standards & Legislations User defined?
Answer
Yes, these can be defined in Core Data > Standards & Legislations.
 
5.7
Reference
Core Data
Question
When starting a job without accepting it, do the events update with an acceptance event?
Answer
No, only the Job Started event is displayed.
 
5.8
Reference
Core Data
Question
Can we collapse and expand Equipment/Service Types in Equipment/Service Types screen?
Answer
Yes and this can be done by double-clicking the type to either expand it or collapse it.
 
5.9
Reference
Assets
Question
Should the Warranty Resource field on an Asset show both manufacturers and resource?
Answer
No.
 
 
6.     Portal – Q & A
 
6.1
Reference
Portal - Client
Question
When a Client raises a job does it duplicate check?
Answer
No.
 
6.2
Reference
Portal - Client
Question
When a job is raised by the Client does it show that the Client raised it on the Work Order?
Answer
Yes it does.  It shows as Web or Agent on the events.
 
6.3
Reference
Portal - Client
Question
Does the Portal automatically log the User out?
Answer
Yes, after 30 minutes of no activity.
 
6.4
Reference
Portal - Contractor
Question
Can contractors do asset tagging and upload certificates from a hand held device?
Answer
Not currently but will be in a future iteration.
 
6.5
Reference
Portal - Contractor
Question
View Building Notes – Can this be turned off for contractors?
Answer
Yes, this is permission based.